Construction Management

A new data centre on a former industrial site at Acton Lane, Park Royal.

We know construction is a key concern for local people. We’ll work with the OPDC to agree measures to minimise disruption and keep residents informed. Construction is expected to take around 24-30 months, subject to planning approval.  

  • Approved construction working hours
  • Designated HGV routes
  • Wheel washing and road cleaning
  • Dust suppression and air quality monitoring
  • Noise and vibration monitoring
  • Temporary acoustic barriers where required
  • Regular communication with nearby residents regarding upcoming works

Air quality will be assessed through the planning process and monitored throughout construction. Measures agreed with the OPDC, including site fencing, water sprays to keep dust within the site and real-time monitoring, will help minimise dust, noise and vibration.

During construction, we’ll use quieter, well-maintained equipment, temporary acoustic screening, plan noisier work for less noise sensitive hours, and always monitor noise and vibration.

Once operational, data centres are very quiet. Most of the sound comes from cooling equipment, which creates a steady background hum that can be compared to a fridge in another room or an air conditioning unit in the distance. At nearby residential locations, the operational noise would blend into the everyday background noise of the area.

We’ve undertaken a Transport Assessment to understand how the development could affect local roads during construction and operation. The assessment considers highway capacity, traffic routes and junctions, and any potential steps we need to take to keep things running smoothly. These measures could include:

  • managing and scheduling deliveries carefully 
  • avoiding busy peak times where possible
  • using designated vehicle routes
  • using travel plans for the workforce
  • coordinating with the local highway authority

There will be a temporary increase in vehicle movements, including HGVs, during demolition and construction. Construction traffic would use the existing access route on Acton Lane. Delivery routes and movements will be carefully managed to minimise disruption.

We don’t expect any permanent changes to local bus routes. Any temporary traffic measures will be agreed with the OPDC and the highways authority and communicated through the Construction Working Group.

Everyone working on site will be encouraged to use public transport, walk, cycle or car share, helping to minimise pressure on local roads. Site inductions for workers will also make clear that parking on the Wesley Estate is not permitted.

Once operational, day-to-day traffic is expected to be lower than the levels when the Industrial Estate was fully occupied. The development would not require regular HGV movements to and from the site, meaning traffic would be much lower than a typical warehouse or industrial site.

We’ll put measures in place to protect pedestrians and cyclists throughout the construction and operational phases, including clearly signed construction site boundaries and maintained pedestrian routes.

Thank you for taking part in our consultation

Our public consultation ran from Monday 7 September to 11:59pm Thursday 24 September 2026.

The feedback received will help shape things like the appearance of the building, landscaping and green spaces, and how construction is managed.